Since 2022, metropolis officers — flush with pleasure — have been touting a modular rest room deliberate for the busy Discovery Playground in Fort Washington Park as a quicker, cheaper technique to construct public restrooms.
The brand new prototype shall be “cheaper to construct and will be put in extra rapidly and with much less disruption,” members of Manhattan Neighborhood Board 12 wrote once they authorized the design in September of that 12 months.
The concept was easy: a prefabricated consolation station constructed offsite and put in atop a big septic tank, eliminating the necessity to connect with metropolis sewer strains.
However practically 4 years later, the mission stays stalled in bureaucratic crimson tape.
“This rest room has been in purgatory with design adjustments and authorized critiques,” Merritt Birnbaum, president and CEO of the Riverside Park Conservancy, informed THE CITY. That group helps handle the river-adjacent inexperienced area.
“In the meantime development prices are going up, and there’s nonetheless no rest room at this location,” she added.
The delays come as Mayor Zohran Mamdani introduced a plan to push the prefab potty idea even additional.
Throughout a press convention in Harlem in January, he directed the New York Metropolis Financial Growth Company to start soliciting bids inside his first 100 days for modular, high-quality public bogs.
“In a metropolis that has every part, the one factor that’s usually inconceivable to search out is a public rest room,” he mentioned.

But when the still-unbuilt Fort Washington Park rest room is any instance, Mamdani’s modular loos could also be years away.
Initially included within the 2022 metropolis funds on the urging of then-Councilmember Mark Levine, who represented elements of northern Manhattan, the mission was slated to value an estimated $3.5 million.
The mission’s design hit some early snags.
The design work — all completed in home by Parks Division workers — was initially slated to conclude by April 2023. But it surely finally took longer, wrapping up in March 2024, in keeping with the Parks mission tracker.
The ability would come with two small restrooms, a consuming fountain and cupboard space inside a modest cube-like construction.
Different elements of the plan acquired backed up, too.
As a result of the toilet web site sits near the Hudson River, the New York State Division of Environmental Conservation needed to weigh in on environmental laws tied to the watershed.
Metropolis officers additionally ended up altering technical components of the design.
Parks engineers raised considerations concerning the authentic air-conditioning system primarily based on points in different tasks, prompting a redesign of the HVAC system, metropolis information present.

The end result: years of design revisions and regulatory critiques whereas development prices climbed by roughly 12% to fifteen%, in keeping with business estimates.
Immediately, the Fort Washington Park playground nonetheless doesn’t have public bogs.
“Dwelling within the neighborhood, there has by no means actually been one round right here,” mentioned Jovanny W., who grew up in Washington Heights and was on the park together with his child daughter Tuesday. In an emergency, he’d use the closest rest room, which is a few 15-minute stroll away, he defined.
“It’s form of odd that there isn’t one, to be sincere,” he mentioned.
A spokesperson for town Division of Parks and Recreation mentioned the mission is a part of the company’s $150 million “Higher Loos” initiative aimed toward upgrading getting old services and constructing new restrooms in parks throughout town.
Parks officers famous that the company has efficiently put in modular loos elsewhere. A prefabricated restroom at Lopez Playground on Staten Island, which opened in 2024, not too long ago received an American Institute of Architects New York Design Award for its modular development.
A spokesperson for Levine, who now serves as town’s chief monetary watchdog, mentioned he “cares deeply” concerning the Fort Washington Park mission however declined to debate the delays or any doable methods to hurry it alongside.
The park’s location close to a flood zone additionally required further structural design and regulatory approvals, officers mentioned.
The following part — “procurement” — started in March 2024 and was initially anticipated to conclude in a 12 months. The town has since pushed that timeline again one other two years, estimating the contracting course of will now stretch via March 2027.
And town nonetheless hasn’t chosen a contractor.
Parks officers estimate the development part sometimes takes 12 to 18 months for tasks of this kind. They’ve lengthy struggled to maintain routine capital tasks on schedule and inside preliminary funds assessments.
Former Parks Commissioner Adrian Benepe, who led the division from 2002 to 2012, mentioned restroom tasks have been probably the most irritating a part of his tenure.
“Loos — or as we used to name them, consolation stations — have been the bane of my existence,” Benepe informed THE CITY. “And this goes again many years. It’s nothing new.”
Even comparatively small tasks should navigate a thicket of approvals, he mentioned, together with critiques by neighborhood boards, the Design Fee, metropolis attorneys, the comptroller’s workplace and funds officers.
“There are at the very least a dozen bureaucratic steps even a easy mission has to undergo,” Benepe mentioned.

Complicating issues additional is New York’s Wicks Regulation, a state statute that may require separate contractors for plumbing, electrical, heating and common development work as soon as tasks exceed sure value thresholds.
“That’s a nightmare for a easy mission,” Benepe mentioned. “You’ll be able to have one contractor be unhealthy and three be good — and that can delay every part.”
Benepe recalled one renovation of a small park restroom that dragged on for a decade.
“I used to say they discovered learn how to get folks to the moon quicker than we will repair a easy bathroom,” he mentioned.
Nonetheless, Benepe mentioned new approaches reminiscent of “design-build” development — the place architects and builders work collectively from the outset — may assist velocity up tasks if town applies them to park infrastructure like restrooms.
The Manhattan rest room saga echoes a infamous restroom mission in San Francisco that turned a nationwide punchline after officers estimated a single public bathroom may value about $1.7 million to construct.
The proposal sparked a political uproar and was ultimately changed with a donated prefabricated unit that value a fraction of the unique value.
On Tuesday afternoon at Discovery Playground, one father mentioned the shortage of a close-by restroom is an everyday frustration.
Alejandro Quintero, 35, mentioned households usually find yourself leaving the playground if somebody wants to make use of the toilet.
“We go over there,” she informed THE CITY, pointing towards a close-by facility a number of blocks away. “But it surely’s very soiled.”
With further reporting from Lilly Sabella.